6-1-04,
1 pic
Amy has her lot
|

9-1-04, 3 pics
Original design by
MossCreek, initial timberframe design by Tennessee Timberframe |

1-20-05, 4 pics
Foundation staked
out by Lonesome Dove Construction, Manufacturing of timber frame in Tennessee
begins |

2-10-05, 4 pics
snow cleared,
footers dug, ground thawed in preparation for concrete
|

2-18-05, 4 pics
footers being
formed and poured
|

2-25-05, 4 pics
foundation walls
being formed, nearly ready to pour concrete foundation walls
|

3-5-05, 4 pics
subfloor
construction, 2 days away from starting the timber frame erection.
|

3-8-05, 4 pics
Timberframe System
delivered to Tamarack! Bents are put together on sub floor before being
erected.
|

3-9-05, 5 pics
Assembled bents in
the timber frame system stand tall on subfloor. Dennis Bolick offers
direction in the timber frame erection process.
|

3-10-05, 28 pics
Amy Koenig, Vice
President of Marketing for Tamarack Resort, visits her job site. She looks
thrilled. Chris Reino, Larry Dammerman, Ed Elliott and Dennis Bolick keep
close tabs on construction. What a beautiful location and timber frame
home.
|

3-11-05, 11 pics
Amy's jobsite is
all quiet now. Larry Dammerman has the place to himself. Thanks for
the pictures Larry. The Douglas Fir timber frame looks fantastic.
There's more frame
to install....stay tuned.
|

3-15-05, 10 pics
More bents are
erected....she's taking shape.
|

3-20-05, 10 pics
The frame is 95%
complete.
|

4-5-05, 6 pics
Structural
Insulated Wall Panels were pre-cut at the factory and offer great energy
efficiency.
|

4-28-05, 8 pics
Amy visits her
jobsite with Larry.
|

8-19-05, 14 pics
Moving right Along.
|

10-1-05, 2 pics
WOW!!!
|

3-23-06, 8 pics
Look at the Outside
|

05-06-05, 14 pics
Look at those
Timbers!
|
|
|
|
|
|
|
|
|
|
|